|
Mould Removal
Click here to view us on the Discovery Channel
After a complete inspection, whether simply a
visual inspection or a complete indoor environmental assessment, where mold is
discovered, removal should be done immediately.
Due to the hazardous nature of mold, removal
should ONLY be done by a Certified Mould
Remediation contractor. Even small areas of remediation should be performed
using containment in order to prevent the spreading of aerosolized spores to
uncontaminated areas during the remediation process.
MSI: specializes in complete remediation of mould
contamination in residential, commercial, industrial and institutional
buildings. We perform all work in accordance with strict industry accepted
Guidelines and Remediation Protocols.
Summary of the Six
Steps of Remediation:
-
Step 1. A
barrier is established to confine the mould and keep it from spreading during
the removal. All surfaces that are not contaminated and are not being removed
are protected using polyethylene sheeting. Negative pressure is maintained in
the containment area for the duration of the remediation using commercial HEPA
grade air scrubbers. During the remediation process the number of mould spores
that become aerosolized may be 1000 times higher. If the area is not contained
properly by a certified contractor, the mould spores may be spread throughout
the building causing extensive contamination.
-
Step 3.
Contaminated framing material, floor sheathing, concrete etc. is cleaned using
wire brushing, sanding, scraping and state of the art dry ice blasting.
-
Step 4.
All areas are damp wiped using an all natural fungicide and receive three
complete passes using a commercial grade HEPA vacuum to remove any settled
spores.
-
Step 5.
Clearance testing is performed at the end of the remediation and before
containment is removed in order to ensure that the mold has been successfully remediated.
-
Step 6.
Reconstruction work is performed to restore the structural and surface
finishing materials to their original state by a General Contractor.
Details of
Remediation
What using MSI:
includes:
General
-
All work will be carried out
by our highly trained and experienced Mould Remediation Technicians under the
direct supervision of our Team Leaders and/or Supervisors.
-
All work will be carried out
in a good workmanlike manner using new materials (unless existing materials
are reused where directed/specified for the particular project).
-
All work will be carried out
in accordance with our company safety policy.
-
$5 million Builder’s All
Risk, Public Liability and Employer’s Liability and a minimum of $1 million
Mould Remediator insurances will be in place for the duration of the
Project.
-
All work will be carried out
in accordance with the applicable Building Codes, the drawings, remediation
protocol, scope of work, specifications, industry guidelines and authorities
having jurisdiction, as applicable.
Personnel
Only Personnel trained in the
handling of hazardous materials will perform mould remediation. Personal
Protective Equipment (PPE) will include:
-
Full-face respirators with
HEPA filtration cartridges for chemicals and organic vapors.
-
Disposable protective
clothing covering head and shoes.
-
Latex, vinyl, neoprene or
nitrile gloves.
-
Work gloves.
-
All our Mould Remediation
Technicians are fully trained in mould remediation and our Team Leaders and
Supervisors are also Certified Hazardous Material Technicians.
Typical
Containment Protocol and Procedure to be used
-
Complete isolation of work
area from other occupied spaces using plastic sheeting sealed with duct tape
or similar materials (including ventilation ducts/grills, fixtures and any
other openings)
-
Negative air machines with
HEPA filters to generate negative pressurization.
-
All contained areas will
include properly sealed plastic sheeting on the ceilings, walls and floors,
other than the work area where materials are to be removed. Depending on the
nature of the project, the work area where mould is to be removed may not
require plastic sheeting on the floors. The walls and ceilings with no
visible mould growth will have plastic sheeting across the ceiling and from
the ceiling down to the floor.
-
In order to properly seal
and create the negative pressure containment the HVAC system may need to be
shut down and sealed prior to any remedial activities. As a precaution, and
whenever practical, the HVAC system will be shut down regardless of whether
this is a necessity. All diffusers, vents and intakes must be completely
sealed within the containment areas.
-
Containment will be erected
using fireproof plastic sheeting of the following densities: Ceiling 4 mil,
Walls 6 mil and Floors 10 mil (where possible).
-
Containment will be
maintained via negative pressure to a minimum of -0.02 inches of water column.
This will be checked and logged daily before and after any activities inside
the contained area as well as periodically during the workday. Containment
pressurization will be operated without interruption 24 hours/day until
completion.
-
Containment area will allow
a minimum of 4 ACR (air changes) per hour.
-
All filters used on site
will be functioning properly and disposed of as sanitary waste at the end of
the work or when necessary to ensure proper functioning. All venting will be
done to the outside of the building where possible, using HEPA filters.
-
All areas will be clearly
marked as ‘Regulated Containment Area' and the containment area will be secure
at all times.
-
All surfaces in the
contained area including containment barriers will be HEPA vacuumed and
cleaned with a damp cloth with a detergent solution and/or Benefect and will
be visibly clean prior to the removal of the containment barriers. Three (3)
passes of HEPA vacuuming for final cleaning will be performed. All equipment
and tools in the containment areas will be cleaned and decontaminated prior to
the removal of containment barriers.
-
Cleaning inside the
containment area will be conducted from clean working areas towards dirty
areas. Cleaning of walls will be from top to bottom and towards the air
filtration device.
-
Contained area will be free
and clear of any debris, dust and mould growth and all surfaces including the
containment barriers will have been cleaned as specified at the end of the
remediation works.
-
Access to the containment
area will be restricted to qualified personnel, and the Client under
supervision, with appropriate Personal Protection Equipment (PPE) only.
Unrestricted access and/or occupancy should not occur until the containment
area has been cleared. Unauthorized entry into the containment area will void
all warranty and liability aspects of the work.
-
Depending on the nature of
the project the containment areas may be video monitored and alarmed in order
to ensure security and prevent unauthorized entry.
-
Vacating people from spaces
adjacent to the work area during mould remediation may or may not be necessary
depending on the exact nature of the project.
Decontamination Area Entry Procedures
Decontamination Area Exit Procedure
The following procedures will
be followed in sequence by all personnel. Before employees leave the
regulated area, they will:
-
continue to wear their
respirators while removing all gross contaminants and debris from their
protective work clothing.
-
Employees will remove their
protective work clothing in the entry room and deposit the clothing into
sealable plastic bags or containers for disposal. Respirators will not be
removed until they have exited the entry room.
-
Respirators will be cleaned
whilst donned in the entry room before exiting to the exterior.
Cosmetic
Damage
-
In order to establish the
containment required, polyethylene sheeting and temporary walls may need to be
constructed and these need to be sealed against the existing wall, floor and
ceiling finishes using adhesive tape and staples. This may result in cosmetic
damage to the finishes in the form of staple holes and on occasions, paint
damage when the adhesive tape is removed.
-
Repair of damage to any of
the existing finishes does not form part of the remediation work – the Client
must ensure that this work is part of the contract with the contractor
performing restoration/rebuild work.
Rebuilding
and Restoration Work
-
Unless specifically noted
otherwise, the contract work is for the cleaning and removal and disposal of
all contamination as detailed and does not include any rebuilding or
restoration work associated with the areas affected by the remediation work.
-
It is the sole
responsibility of the Client to arrange, at their sole expense, for a General
Contractor to perform any and all rebuilding and restoration work.
-
Where structural members
require removal for whatever reason i.e. if they are heavily contaminated and
cannot be cleaned, MSI: will reinstall new members in order to retain the
structural integrity. The additional work will be performed on a fixed price
or a time and material basis as agreed with the Client prior to removal of any
structural members.
On-site &
Off-site Cleaning of Possession and Contents
-
If noted as part of the
scope of work, personal possessions, contents, etc. will be cleaned using HEPA
vacuuming and /or damp wiping with anti-bacterial soapy water or Benefect.
Porous items CANNOT be effectively cleaned and should be disposed of.
Absolutely no warranty is provided with respect to the cleaning of all porous
items such as but not limited to sofas, chairs, mattresses, drapes, blinds,
paper products, etc. The Client will accept all responsibility for porous
items that the Client chooses to retain.
-
All items showing visible
mould growth should be disposed of. If requested by the Client items showing
mould growth will be cleaned as best as possible. Absolutely no warranty or
guarantee whatsoever is provided with respect to the complete removal of
contamination using on-site cleaning techniques.
-
For comprehensive cleaning, all contents should be packed out
and transferred out our warehouse cleaning facility for complete cleaning and
decontamination. Once cleaning is completed the contents are repacked and
stored until remediation work is completed. Additional costs apply for all
cleaning, moving and storage.
-
No liability is accepted for damage to
personal property, effects and possessions not cleared from the work area or
cleared and cleaned by our personnel.
-
All items within the work
area that are to be cleaned and retained are to be listed in writing by the
Client on a ‘Retained Item Inventory List’. No liability will be accepted for
items disposed of that are not specifically noted on the ‘Retained Item
Inventory List’.
Kryoblasting using Dry-Ice
-
Where Kryoblasting is
specified for a particular project this involves the use of dry-ice blasting
technology. “Rice” grains of dry-ice (frozen carbon dioxide) are used as the
abrasive material and are fired, under pressure, using compressed air against
the substrate being cleaned. Upon impact the rice grains sublime (change from
solid to vapour state without becoming a liquid) and become carbon dioxide
which is vented to the exterior using the negative air machines. The
remaining residue that was removed from the substrate is then simply
cleaned-up using standard remediation techniques. There is NO
carbon monoxide produced in this process and there is no toxic pollution
created.
-
The compressor which runs
the blaster is a trailer mounted diesel motor powered unit which must be
located on the exterior of the building structure within 25’ of a means of
entry (i.e. a door or window).
-
The blaster unit is located
inside the structure, usually outside of containment wherever possible in
order to allow for easy loading of the “rice”.
-
The use of the compressor
and Kryoblaster is a noisy process and ear protection is required for all
employees. The adjacent space may need to be vacated during blasting
operations if the noise level is found to be excessive by the occupants.
-
The carbon dioxide in its
gaseous state during the blasting operation and when being vented to the
exterior is often in a white smoky cloud. There is no danger from this cloud
but the use of the equipment is not discrete.
Changes in
Site Conditions
-
On site conditions, Client,
occupant or third party actions, structural or building envelope system,
mechanical system, as well as the passage of time may alter or have altered
the overall conditions and environmental status and/or hazards of the areas in
question since this inspection and remediation protocol were established.
-
If the conditions are
different at the start of the project than at the time of the inspection and
preparation of the remediation protocol then work will not commence until a
revised contract is prepared and agreed to by all parties.
Moisture
-
The underlying cause of
moisture and water accumulation indoors must be rectified to avoid fungal
growth.
-
All water intrusion must be
rectified, by others and all building materials and surfaces must be
completely dry before areas are rebuilt.
Duration of
the Project
-
The anticipated duration of
the project is an estimate of the time required to complete the project on
consecutive days from the start date. Mould remediation is a complex process
and often the full extent of the work is not known until the work commences.
MSI: will not be held liable in any way for time overruns associated with
completing the work.
-
Where unforeseen conditions
or changes occur, either associated with the findings during remediation or
additional work requested by the Client, then the duration of the project will
be extended by the time required to complete the additional work.
Use of
Chemical
-
Our policy on mould
remediation is that the work is done to remove the contamination and we do not
use any chemical remediation processes as these are often ineffective and can
produce additional problems associated with the chemicals themselves. In
addition, in the case of moulds that produce mycotoxins, the toxin is not
removed from the mould spores when they are killed using chemicals therefore
the toxic effect on the body caused by the mould spores when inhaled is
unchanged.
-
At the end of the
remediation process all affected areas are treated with Benefect solution.
This is an all natural anti-bacterial and anti-fungicidal solution. Since
mould spores are naturally in all the ambient air it is impossible to remove
every spore. The use of Benefect helps to ensure that future mould growth
does not occur and also disinfects the work area.
-
The Benefect solution has a
citrus type odour which is fairly sweet smelling. This smell will gradually
diminish and will be undetectable after 7to10 days.
-
Under no circumstances will
chemical biocides, anti-microbial solutions, encapsulates, sealants, gaseous
ozone, chlorine dioxide or bleach etc. be used as mould remediation methods
/tools.
Hazard
Communication
-
When fungal growth requires
large-scale remediation, the Client, building owner, manager or employer must
notify occupants in the affected area and adjacent areas. Notification should
include a description of the remediation measures and a time frame for
completion.
-
Individuals with persistent
health problems that appear to be related to bioaerosol exposure should see
their physician immediately. Individuals seeking medical attention should
provide all information available with respect to the mould contamination to
their medical practitioner.
-
Containment entry areas will
have warning signs posted conveying clearly that the containment area is
restricted and no unauthorized entry is permitted under any circumstance.
-
The potential serious nature
of the work and the effect on the individuals health if they disregard the
warnings must be stressed as part of the Hazard Communication.
Post
Remediation Clearance Inspection
-
If specified or required by
the Client, Post Remediation Clearance Inspection and Testing can be performed
either by MSI: or by a third party.
-
Negative pressure will be
maintained until after confirmation from the inspector that the containment
can be removed. Air scrubbers will be shut down 6 hours prior to the
inspection and all other equipment, tools, etc. will be decontaminated and
removed from the containment prior to the inspection.
-
Samples taken at the
inspection will be processed within a 24 to 48 hour time frame. Clearance
shall only be granted after these results are available. Containment will not
be removed until written clearance is provided.
-
The cost of clearance
inspection will be the responsibility of the Client.
-
If for any reason the
clearance inspection results in a requirement for additional cleaning on the
part of MSI: then the cost of a re-inspection will be paid by MSI:.
Furnace and
Duct Cleaning
 |